Home > Oil > YINKA FOLAWIYO’S AJE OML 113, $250M GAS PROJECTS SUFFER FINANCIAL SETBACKS

YINKA FOLAWIYO’S AJE OML 113, $250M GAS PROJECTS SUFFER FINANCIAL SETBACKS

Folawiyo’s operated Aje Field, OML 113 offshore Nigeria, and his partners are currently finding it difficult to pull through the running and development of the project.
The field is operated by Yinka Folawiyo Petroleum. Other members in the Aje Joint Venture are New Age, Energy Equity Resources, Mx Oil, and Panoro.
The challenge between the partners which started as far back as 2016, is yet to be fully resolved, leading to other proposed projects such as the development of the gas reservoir to be put on hold.
Besides, the gas project will cost nothing less than $250 million but has been put on hold as partners now plunge revenue realised into running the oil field. The partners had anticipated drilling three or four wells to produce over 500 billion cubic feet of gas, 22 million barrels of condensate and 40 million barrels of liquefied petroleum gas.
The Aje field itself was planned to produce 10,000 barrels per day of crude for at least the first three years however, we learned has been churning out just 3,150b/d, making it difficult to realise measurable gains.
As a result of underperformances, the “partners are more concerned with keeping the running cost flowing. The field is not making a profit as expected,” one of our sources said.
According to reports, in February, the partners are reprocessing three-dimensional seismic data in search of new interpretation for development of two new wells, 6 and 7 – technical work are still ongoing on the field.
Professional services firm of consultants and service providers, headquartered in Abingdon, U.K, RPS Group, was appointed in late October 2018 to conduct an assessment of the potential development activity associated with the additional field.
RPS is expected to finish its work in Q1 2019 and will form the basis for a decision on further drilling of phase two.
In preparation for the anticipated potentials of the two new fields, it was understood that the partners have since begun steps to procure debt funding for Phase 2 and other potential future stages and that discussions will continue into the first quarter of this year before final decisions will be taken.
In 2018, production from the two wells in the Aje field achieved a total volume of around 1,200,000 barrels of oil.
The partnership completed the ninth lifting from the Aje field in late November 2018 off-taking approximately 315,000 barrels of oil. The tenth lifting occurred in late February this year.
The JV partners encountered first oil of about 7,000 barrels per day on May 3, 2016. Oil produced from the field is stored on the Front Puffin FPSO which has a production capacity of 40,000 barrels of oil per day and storage capacity of 750,000 barrels.
In 2018, the Aje partners, paid the sum of $9.8 million for another 20 years renewal.
Hopefully, the renewal will yield positive results for all partners depending on progress of the project.

Energy Focus